St. Johns – Cathedral Park Sewer Repair Project Update: November 9, 2018

Environmental Services has begun construction on a project to repair over 11,000 feet, or about 2 miles, of public sewers in the St. Johns and Cathedral Park neighborhoods. Many of the sewer pipes are about 80 years old and deteriorating due to age. This investment in your neighborhood will allow for continued dependable sewer service and protect the public and our environment by reducing the possibility of sewage releases to homes, businesses and streets.

CONSTRUCTION SCHEDULE

Construction began mid-September 2018 and will take about a year to complete. Depending on the location and construction method, work could last up to a month or more in one area. For the most up-to-date information and map of the project schedule, visit www.portlandoregon.gov/bes/StJohnsCPark.

 

Week of November 12:

  • Crews will repair the sewer mainline on N Trumbull Avenue between Hudson and Smith Streets using open trench construction. This will take about two more days to complete.

  • Crews will repair the sewer mainline on N Hudson Street between Trumbull and St. Louis Avenues using open trench construction. This will take about a week to complete.

  • Crews will repair a few lateral pipes on N Macrum Avenue between Mears Street and Columbia Boulevard. This will take about three days to complete.

  • Crews will repair the sewer mainline on N Mears Street between Oregonian and Macrum Avenues using open trench construction. This will take about a week to complete.

 

Week of November 19 (no work on November 22 and 23 for the Thanksgiving holiday):

  • Crews will repair lateral pipes on N Trumbull Avenue between Hudson and Smith Streets and lateral pipes on N Hudson Street between Trumbull and St. Louis Avenues. This will take up to a week to complete.

 

Crews will continue installing manhole steps in the work areas below. This work will take approximately one day to complete each area.

  • N Trumbull Avenue between Hudson Street and Smith Street

  • N Hudson Street between Trumbull Avenue and St Louis Avenue

  • N St Louis Avenue between Hudson Street and Smith Street

  • N Central Street between Bristol Avenue and Trumbull Avenue

  • N Central Street between Trumbull Avenue and St Louis Avenue

  • N Columbia Boulevard between Midway Avenue and Oregonian Avenue

CONSTRUCTION METHODS

The city uses many construction methods to repair or replace sewer pipes. For the upcoming sewer line repairs, the city plans to use Open Trench Excavation. To learn more about different constructions methods and what can be expected during construction, go to www.portlandoregon.gov/bes/methods.

 

WHAT TO EXPECT DURING CONSTRUCTION

We have started some pre-construction activities and you may see crews working in your neighborhood. Activities could include documenting pipe conditions via video cameras; fencing off trees for protection; tree trimming; equipment use and storage; noise, vibration and dust; traffic delays, and parking restrictions.

 

Typical work hours are 7:00 a.m. to 6:00 p.m. Monday through Friday, but the contractor may schedule work during the same hours on Saturdays.

 

Residents and businesses should expect periods of inactivity between phases of work, ranging from a few days to a few weeks. In areas where the repair requires a trench, temporary pavement will be applied to the site until permanent pavement can be applied at a later date. The duration of any period of inactivity depends on a variety of variables including underground conditions, weather, traffic impacts, subcontractor schedules, quality control tests, and availability of materials. In the event of a sewer backup, storm drainage problems or clogged catch basins, call 503-823-1700.

 

To learn more about what to expect during construction go to www.portlandoregon.gov/bes/constructionimpacts.

 

KEEPING YOU INFORMED

The city’s goal is to keep businesses and residents informed during construction. The latest project information is available in several ways:

·      Mailings: Project updates will be mailed throughout project construction.

·      Website: The latest construction schedule and project updates will be available at: www.portlandoregon.gov/bes/StJohnsCPark

  • Email Updates: To sign up for email updates, email Jessica@jla.us.com with “St. Johns – Cathedral Park Sewer” in the subject line. If you include your address, we can provide you with specific construction information about your location.